2014 Road project status updates

District 1 project map     |      District 2 project map     |     District 3 project map

Project overview information     |     Magnesium chloride applications

Please do not park any vehicles along the roads during chip-seal or asphalt applications.

District 1
  CR 103 - Crystal Springs road  
County Road 55 CR 55, 57, 59

cr103 sm

 

traffic cone
100% complete

Paving is done, shoulder work to be completed 7/15-7/18

Paving is scheduled to start Monday June 30th on County Roads 100 and 103.

This project will begin just north of Hwy 82 and extend for 4 miles to the intersection of CR 100. It will include .9 miles of CR 100 ending at the intersection with CR 113. A 2” asphalt overlay will be placed to re-establish water drainage off the road improve surface conditions. Preparation activities will include cleaning ditches, culverts and any necessary shoulder work.

  • Preparation Activities: Week of April 21, 2014
  • Estimated duration: 4 days
  • Resurfacing by Contractor: TBA
  • Estimated duration: TBA
  • Expected Delays: Minimal
  • Alternate Route: SE on CR 100 to Hwy 82; SW on CR 113 to Hwy 82
     
CR 293 - North Graham  
County Road 69 Westbank

 

293 before

traffic cone
100% complete
5/21/14 - Paving on CR's 293 and 294 is starting today.

This project will begin at the “Y” intersection where both roads meet. It will extend SW on CR 294 for .4 miles and north on CR 293 for .6 miles ending at the Rifle City Limits. A 2” asphalt overlay will be placed to re-establish water drainage and improve surface conditions. Preparation activities will include cleaning ditches and culverts along with any necessary shoulder work.

  • Preparation Activities: TBA
  • Estimated duration: TBA
  • Resurfacing by Contractor: TBA
  • Estimated duration:
  • Expected Delays: Minimal
  • Alternate Route: W on 16th St. to Railroad Ave; or W on Third St. to Whiteriver Ave.
 
     
  CR 294 - S Graham road  
County Road 106 CR 106

cr294 before

traffic cone
100% complete
5/21/14 - Paving on CR's 293 and 294 is starting today.

This project will begin at the “Y” intersection where both roads meet. It will extend SW on CR 294 for .4 miles and north on CR 293 for .6 miles ending at the Rifle City Limits. A 2” asphalt overlay will be placed to re-establish water drainage and improve surface conditions. Preparation activities will include cleaning ditches and culverts along with any necessary shoulder work.

  • Preparation Activities: TBA
  • Estimated duration: TBA
  • Resurfacing by Contractor: TBA
  • Estimated duration:
  • Expected Delays: Minimal
  • Alternate Route: W on 16th St. to Railroad Ave; or W on Third St. to Whiteriver Ave.
     
CR 312 - Garfield Creek road  
County Road 112 CR 112 cr 312 small
traffic cone
100% complete
Garfield Creek - Paving start date is schedule for 8/18

Garfield Creek will begin at the intersection of CR 335 and extend south for 8 miles. The road will be milled and gravel will be added before a 4” asphalt overlay will be placed. Preparation activities will include culvert cleaning, extensions and/or replacements as needed. There will also be ditch cleaning and shoulder work activities.
  • Preparation Activities: Week of April 14, 2014
  • Estimated duration: 2 weeks
  • Resurfacing by Contractor: TBA
  • Estimated duration: TBA
  • Expected Delays: Minimal
  • Alternate Route: There is no alternate route, please watch for road crews and plan for timing and safety.
     
  CR 314 - Alkalai Creek  
314 small
CR 114
traffic cone
100% complete
Chip sweeping and fog seal to take place 7/15 - 7/18

Chipseal will begin on CR 314- Alkalai Creek and Mountain Shadows Subdivision on Wednesday July 9th.

Paving has taken place, Chipseal is still pending. Driveway aprons will be taken care of after chipseal has been completed.

  • Expected Delays: Minimal
  • Alternate Route: There is no alternate route, please watch for road crews and plan for timing and safety.
     
  Mountain Shadows Subdivision
CR 462, 463, 464, 465, and 467 Apricot Circle, Cherry Ct., Peach Ct., Pear Ct., and Plum Ct.
 
  cr240

mtn before

traffic cone
100% complete
Chip sweeping and fog seal to take place 7/15 - 7/18

Paving has taken place, Chipseal is still pending. Driveway aprons will be taken care of after chipseal has been completed.
  • Expected Delays: Minimal
  • Alternate Route: There is no alternate route, please watch for road crews and plan for timing and safety.
 
 
 
Road & Bridge Administration
District 2-3 facility
0298 County Road 333A
Rifle, CO 81650
Email Road & Bridge


970-625-8601 | phone
970-625-8627 | fax
  Road & Bridge
District 1 facility
7300 Highway 82
Glenwood Springs, CO 81601
Email Road & Bridge


970 945-1223 | phone
970-945-1318 | fax
   
 
privacy policy