District 1
  CR 113 - Cattle Creek Road  
County Road 55 CR 108

sm

 

traffic cone
100% complete

Update: Paving will start Tuesday, July 5th and last a duration of 2 weeks -/+.

This project will begin at the intersection of Highway 82 and County Road 113 and end at County Road 122 for a total of 8.6 Miles. A 2" asphalt leveling course will be laid, 3" over the gravel portion. Preparation activities will include cleaning ditches, culverts and any necessary shoulder work.

     
District 2
CR 226 - Grass Valley Road  
County Road 69 cr 204

 

cr 226 small

traffic cone
100% complete

This project will be for the entire 7.5 Miles of CR 226 - Grass Valley. The road will be milled, followed by 2" of gravel followed by a 2" asphalt mat. Preparation activities will include culvert cleaning and/or replacement as needed. There will also be ditch cleaning and shoulder work activities.
 
     
  CR 455 - Rainbow Drive  
County Road 247 CR 247

cr 455 small

traffic cone
100% complete
This project will begin at Odin Drive and end at Asgard for a total length of .19 Miles. A 2" asphalt mat overlay will be placed. Preparation activities will include ditch cleaning.
     
District 3
CR 321 - Taughenbaugh Mesa  
cr 259 CR 259  
traffic cone
100% complete

This project will begin at the Intersection of CR 320 & CR 321 and extend the entire length of the road, or 2.2 Miles. The road will be milled, 4" of gravel followed by 3" asphalt overlay. Preparation activities will include culvert cleaning, extensions and/or replacements as needed. There will also be ditch cleaning and shoulder work activities.
     
traffic cone Rifle Village South - CR357 sections listed below

Paving is expected to start September 5 and be completed September 8, with Shouldering immediately following.
 
  CR 357A - Village Drive  
cr 260 village drive small
cr 357
traffic cone
100% complete
     
  CR 357 - Remington Street
 
cr 300O cr 300

Remington street small

traffic cone
100% complete
  CR 357B - Colt Drive
 
cr 302 cr 302

Colt drive small

traffic cone
100% complete
  CR 357C - Browning Drive
 
cr 303 cr 303
Browning small
traffic cone
100% complete
  CR 357D - Shotgun Drive
 
cr 335 cr 335

shotgun before small

traffic cone
100% complete

This project will encompass all the Rifle Village South roads as listed above. There will be a 2" asphalt overlay placed. Preparation activities will include culvert cleaning, extensions and/or replacements as needed. There will also be ditch cleaning and shoulder work activities as required.
 

 


 
 

 

 
 
 
Road & Bridge Administration
District 2-3 facility
0298 County Road 333A
Rifle, CO 81650
Email Road & Bridge


970-625-8601 | phone
970-625-8627 | fax
  Road & Bridge
District 1 facility
7300 Highway 82
Glenwood Springs, CO 81601
Email Road & Bridge


970 945-1223 | phone
970-945-1318 | fax
   
 
privacy policy