2015 Road project status updates

District 1 project map     |      District 2 project map     |     District 3 project map

Project overview information     |     Magnesium chloride applications

Please do not park any vehicles along the roads during chip seal or asphalt applications.

District 1
  CR 108 - Thompson Creek  
County Road 55 CR 108

 

 

traffic cone
100% complete

This project is 100% completed..

     
CR 204 - Roan Creek  
County Road 69 cr 204

 

204 sm

traffic cone
100% complete
Update: Start date 10/5/15

This project will begin at The Cowboy Chapel & CR 211 - Clear Creek and continue northwesterly to CR 209 -Brush Creek for 4 Miles. The road will be milled before a 4" asphalt overlay will be placed. Preparation activities will include culvert cleaning, extensions and/or replacements as needed. There will also be ditch cleaning and shoulder work activities.Paving expected to start 8/17/15.
 
     
  CR 247 - N. Cut-off Road  
County Road 247 CR 247

247 small

traffic cone
100% complete
This project will begin at the Intersection CR 226 - Grass Valley Road and extend the entire length to the Intersection of CR 245 - Buford Road for 2.5 Miles. The road will be milled before a 4" asphalt overlay will be placed. Preparation activities will include culvert cleaning, extensions and/or replacements as needed. There will also be ditch cleaning and shoulder work activities. Start around 9/7/15.
     
CR 259 - Jewell Lane  
cr 259 CR 259  
traffic cone
100% complete
This project is 100% completed.
     
  CR 260 - Tippitt Lane  
cr 260  
CR 260
traffic cone
100% complete
This project is 100% completed.
     
  CR 300 - Old Stone Quarry Road
 
cr 300O cr 300

300 small

traffic cone
100% complete
Update: Started 9/9/2015 and should finish 9/24/15

This project will begin at the Intersection of CR 300 - Stone Quarry to the South and extend 1 Mile to the Northerly intersection of CR 300 - Stone Quarry Road. The road will be milled and gravel will be added before a 4" asphalt overlay will be placed. Preparation activities will include culvert cleaning, extensions and/or replacements as needed. There will also be ditch cleaning and shoulder work activities. Paving in September.
  CR 302 - Underwood Lane
 
cr 302 cr 302

302 small

traffic cone
100% complete
Update: Started 9/9/2015 and should finish 9/24/15

This project will begin at the Intersection of CR 300 - Stone Quarry Road and extend to the Intersection of CR 308 - Four Corner Road for a distance of 8/10th of a mile. The road will be milled and gravel will be added before a 4" asphalt overlay will be placed. Preparation activities will include culvert cleaning, extensions and/or replacements as needed. There will also be ditch cleaning and shoulder work activities. Paving in September.
  CR 303 - Gardner Lane
 
cr 303 cr 303
303 small
traffic cone
100% complete
Update: Started 9/9/2015 and should finish 9/24/15

This project will begin at the Intersection of CR 300O - Old Stone Quarry Road and extend to the Intersection of CR 308 - Four Corner Road for a distance of 8/10th of a mile. The road will be milled and gravel will be added before a 4" asphalt overlay will be placed. Preparation activities will include culvert cleaning, extensions and/or replacements as needed. There will also be ditch cleaning and shoulder work activities. Paving in September.
  CR 335 - Colorado River Road
 
cr 335 cr 335

cr 335 small

traffic cone
100% complete
This project is 100% completed.

This project will begin at the I-70 Interchange and extend to CR 314 - Alkali Creek for a distance of 2 Miles. The road will be milled and gravel will be added before a 4" asphalt overlay will be placed. Preparation activities will include culvert cleaning, extensions and/or replacements as needed. There will also be ditch cleaning and shoulder work activities. Paving in August.
  CR 346 - Rifle/Silt Road
 
cr 346 cr 346

cr 346 small

traffic cone
100% complete
This project is 100% completed.

This project will begin at the Intersection of CR 315 - Mamm Creek Road and extend to the Intersection of CR 331 - Dry Hollow Road for a distance of 3.5 Miles. A 2" asphalt leveling course will be laid, followed by 3/4" chips. Preparation activities will include cleaning ditches, culverts and any necessary shoulder work.
 
 
 
Road & Bridge Administration
District 2-3 facility
0298 County Road 333A
Rifle, CO 81650
Email Road & Bridge


970-625-8601 | phone
970-625-8627 | fax
  Road & Bridge
District 1 facility
7300 Highway 82
Glenwood Springs, CO 81601
Email Road & Bridge


970 945-1223 | phone
970-945-1318 | fax
   
 